Supplier effects Ormen Lange 2008-2012

Supplier effects Ormen Lange 2008-2012

Forfatter(e):

Bjørn G. Bergem, Arild Hervik, Oddmund Oterhals

Utgiver:

Møreforsking Molde AS

Oppdragsgiver:

A/S Norske Shell

Rapportnr:

1405
|

Isbn/Issn:

978-82-7830-195-1

Publikasjonstype:

Rapport
|

Sidetall:

27
download

This report summarises the results of a survey of regional supplier effects linked to investments and operations for the Ormen Lange project in the period 2008-2012. Of total expenditures amounting to NOK 35.8 billion in the period, 17 per cent are linked to regional deliveries of goods and services from Central Norway. The regional share is 12 per cent for investments, and 35 per cent for operations. Overall calculations reveal that the regional share associated with operations is consistently higher than for investments, and also consistently higher than the expectations in the impact assessments prior to the field development.